Hi everyone, hope someone can help me.
Within my jira project, I have several Stories, Tasks and sub-tasks. With Jira automation, the story/task will be automatically progressed when all of the sub-tasks are done (for example).
But now I'm facing an issue which I'm not able to solve. Hope that someone within this community can help.
I would like to make the due date of the parent dependent on the nearest/shortest due date of their sub-tasks. For example:
Story --> due date is empty during creation
Sub-task 1 --> due date is 01.04.2021
Sub-task 2 --> due date is 06.04.2021
Sub-task 3 --> due date is 31.03.2021
The due date of the parent should also be 31.03.2021 automatically.
How to do that?
Did you try using "Issue Key" mapping? It should force import to create issues with specified Issue Key
WOO HOO! THANKS. Works like a charm. And not nearly as hokey. ;)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You'll need to pad the numbers and then delete after importing dud issues.
If you have ABC-1, ABC-1, ABC-2, ABC-5, then you need to import ABC-1, ABC-2, ABC-3, ABC-4, ABC-5 and delete ABC-3 and 4 afterwards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
So I had thought of this and thought, "that's just hokey". But it does work. So thanks for suggesting the hokey. :)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.