Hi ,

We are using Tempo for Log time and we also have the Jira Field Time Tracking(Time Spent,Remaining Estimate,Original Estimate).

 

The Estimation fields are useful but for time spent we want to use only Tempo.

Is there any way to make read-only of field "Time Spent" only and keeping Original and Remaining Estimate. 

 

Note: I have eliminated "Log work" from Issue View--> More. In issue screens, we are using Time Tracking field. We want to keep only Original and Remaining Estimate and disable Time Spent

 

 

1 answer

1 accepted

0 votes
Answer accepted
Jason Hensler
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
February 11, 2013

I would give this guide a read -> https://confluence.atlassian.com/display/JIRA052/Integrating+JIRA+with+Apache+using+SSL

It would require setting up apache but, the idea is to have https/ssl configured to secure the traffic.

Suggest an answer