Can't Complete Sprint

Deleted user
October 17, 2016

Hi 

 

I have two custom workflows one for stories and one for sub tasks. 

 

In my current sprint all my stories are set to Status Done and Resolution Done 

all my Tasks are Status - Task Done (Maps to Done see attachment) and resolution Done

 

And I cant complete the print. I have added a JQl to try find and rogue taks or stories but i cant.

 

Any ideas (see attachment) 

TASK DONE MAPPED.png

Stories Done.png

1 answer

0 votes
Mike Sorensen
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
July 8, 2015

For our Final Review step, we assign the issue to the Reviewer which is a simple change to make. You can do things like assigning the issue to someone in a certain role. 

You should also be able to setup a script to do the assignment if one of the canned macros don't work for you. 