Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,560,000
Community Members
 
Community Events
185
Community Groups

How can i create a 3 level hierarchy between epis story and task?

I am creating a board for QA/QC and want a 3 level relationship between epic-story-task.  I have been able to create epic story and task individually but I am clueless about creating link between these three.

4 answers

1 vote
Milan Chheda [INFOSYSTA]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Jun 19, 2019

In order to have 3-level hierarchy, you will have to configure Epic-story relationship first (which is available out-of-box). Once that is done, you can have sub-tasks under stories. So each story can have many sub-tasks. That would give you 3rd level hierarchy of relationship.

I was able to create Epic > Task > Sub-task in order to achieve the 3-level, now the problem is both Epics and Tasks come up the main Board of the project and it created confusion on the users. Is there any way to hide Tasks from the main board and just show the Epics?

@Alejandro Pimentel - have you solved it? I have the same issue... Thx!

0 votes
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Jun 20, 2019

Hello,

You can have a look at the Structure plugin. It will let you see all your issues in a hierarchy.

0 votes
Deleted user Jun 19, 2019

Hi @Maham Faiz ,

As Tony said Story and Task are both at the same hierarchy level in JIRA. Instated of Task, if you use sub-task then it comes under the hierarchy in JIRA. Like Epic - Story - Sub-task.  

Coming to linking of issues you can do this, Click on the more (...) button on the right side of an issue (more) -> Link -> Jira issue. For more information, you can refer to Linking issues page.

Regards,
Kishore Kumar Gangavath.

Maham,

Story and Task are both at the same hierarchy level in Jira. You can establish one-to-many relationship between Epic and Story/Task by update the Epic Link field or you can drag-n-drop the Story/Task from your backlog to the created Epics. You can also create a link between Story and Task but it will not in a hierarchy fashion.

Hope this answer help.