Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,456,701
Community Members
 
Community Events
176
Community Groups

Done status don´t close the task

Hello Community,

 

i have the problem after adding a Status to the Workflow my task don´t close anymore.

i have 24 Done tasks in my sprint and when i try to close the Sprint i got a message 24 task are open 0 Done Move the open tickts to next Sprint (Sprint Selection)  

The tasks are all done but Jira say they are not closed?

Jira puts all the done tickes in the next sprint!

what can i do that jira close a task on status done???

 

Bildschirmfoto 2022-02-16 um 18.07.31.png

 

 

1 answer

0 votes
John Funk Community Leader Feb 16, 2022

Hi Robert - Welcome to the Atlassian Community!

Is your Done status in the very last column? Only issues in the last column are considered completed, regardless of the status. 

Hi John, yes in last column in the workflow and in the borad config to... 

it was the board config, i don't save them correctly now it works - thanks a lot!

John Funk Community Leader Feb 16, 2022

Can you share a screenshot of the board configuration with the columns?

John Funk Community Leader Feb 16, 2022

Ah, very good - glad it is solved!

"Only issues in the last column are considered completed, regardless of the status."

I believe this made sense before Jira introduced multiple "done" statuses. Does seem like a missed feature or a regression when multiple done statuses were introduced. Sounds like it is working as intended (our stories with abandoned status stayed there after closing the sprint) but is confusing as we expected "done" statuses not to flow into the next sprint.

Is there an existing feature or bug request I can follow?