How can I set the dependency between Epics On JIRA project board.
ex. Epic 1 is dependent on Epic2
How can I set this up , so that Epic 1 will be considered as 100% done when Epic 2 is also completed 100%
Note - I tried Linking both the Epics but still it’s allowed to Done for EPic1
Go to your board and turn on "roadmap-beta"
Then there were will a roadmap link on the left side - you can then not only add start and due dates but also click the end of epic 1 and bring to beginning of epic 2.