Calculating with dates in eazyBI

Hi,

 

two questions in eazyBI:

1) I have two fields of issue type "Date Picker". I'm looking for a function similar to average resolution days but I need the time between the two customfields and not from created to resolved. If i use something like 

[Measures].[Field B] - [Measures].[Field A]

i get an error. Also it only shows the error message, when I drill down into the single issues. If i only drill down until the issue level (e.g. "Bug"), I only get a blank field.

 

2) It's almost the same question but for fields of issue type "Date Time Picker". Here I was awaiting a timedifference in hours or minutes but also only got an error.

 

Can anyone provide a correct calculation for the fields?

 

Thanks in advance

Jan

1 answer

1 accepted

0 votes
Answer accepted

Hi Jan,

 

In that case, you could ensure that you have imported these date fields as Issue properties and then you could try using "DateDiffDays" and "DateDiffHours" functions to calculate the difference between two date or date/time fields on Issue level.

DateDiffDays(
[Measures].[Issue Actual start date],
[Measures].[Issue resolution date]
)

 

difference in days.jpg

calculate difference between date fields.jpg

 

 

Here you could read more about DateDiffDays function

https://docs.eazybi.com/display/EAZYBI/DateDiffDays

 

In a similar way, you could create a new calculated measure for DateDiffHours or DateDiffMinutes by choosing an appropriate formatting for it. 

 

Please contact support@eazybi.com if you have further questions regarding this!

 

Kind regards,

Martins Vanags / support@eazybi.com

Hi Martins,

 

thanks, that was exactly what I was looking for.

 

Kind Regards,

Jan

Na I'm New Here Apr 27, 2021

Hello, 

If I need to measure average working time from when a task is in progress until it is solved, taking away the time you spend in an impeded or blocked state

¿?


[Measures].[Average days in transition status],
[Transition].[In Progres-->Resolveds] - [Transition].[blocked]

 

Thank you

Hi, @Na 

 

The closest solution for your use case could be the approach used in one of our Demo reports: https://eazybi.com/accounts/1000/cubes/Issues/reports/499777-average-lead-and-cycle-time.

 

Please, check the formula behind the Average resolution days since the cycle start measure. That is the solution to calculate time from the first transition to a specific status till the resolution.

 

Kindly,

Janis, eazyBi support

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Jira

⏰ Day in the life of a Jira Admin!

Hello Community! We thoroughly enjoyed this just-for-fun conversation in the Jira Admin Group about what it's like to be a Jira Admin. For #JiraJuly, our talented designers created these graphics t...

378 views 2 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you