Swimlane = Multiple projects
Column = Status
My projects are the swimlanes and I want their counts to be distributed per column, is there a way?
Hello @Brendon Kyle Adaya
There is no direct relationship b/w swimlanes and columns. Swimlanes are just categorization of tickets based on a certain criteria (like component, labels etc) whereas Column are issue statuses and that's why both are perpendicular to each other.
If you have 5 column but 10 swimlanes then how will JIRA distribute the issue count across the columns, this is not something supported nor does this make much business sense to do implement it.
Column only shows the count which is based on the issues having the status which is mapped to the column.