Hello all,
I would like to see the done items have been completed in a sprint. I cannot have sprint report since it's a team-managed project. Therefore, I need to filter them.
When I filter with a sprint value, it shows me the issues contains that sprint and the next sprint in addition to the issues that completed in that sprint. Here is the example attached;
I would like to see the issues completed in Sprint 82 but there are the items completed in Sprint 83 as well since they were not completed in Sprint 82.
Hi @Berkan Suna ,
In a team managed project, you can use the Sprint Burndown chart report to get the information you want. Below the chart, there are a few lists with issues, one of them being the list of issues completed in the sprint.
With that list comes a link to view the issues in the issue navigator. And then from there, you can export the issues to e.g. Excel.
Hope this helps!