Hi, since the update to new JIRA I cannot find anywhere how to change the remaining estimate of a task. I can see that the ORIGINAL estimate can change, but how can I edit the REMAINING estimate? This is a must eg. for cases that someone has over/under estimated a task or change of approach that can affect the remaining time of a task.
Yes this is missing from the new UI. You will need to switch back to the old view to make that change - it can be done on a per ticket basis, by clicking on See the old view at the top of any open ticket
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No idea, hopefully before they switch off the old view permanently ;-)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi!
Did ypu find any solution?
Best regards!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The only way I know of to do this is to switch to the old view, which is a nuisance. Hopefully at some point Atlassian will change the new view to match the old one with regards to the estimate section.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.