Hi everyone,
I’m running into something odd. The Priority field in my project is showing up, but it looks like it’s frozen. It is stuck on “Medium,” and I can’t click the dropdown or make any changes.
I’m not sure if this is something I’m doing wrong, if it’s a permissions issue, or if Priority is just not meant to be editable in certain setups. Has anyone else run into this? Is there a setting or configuration I should check, or is this something only admins can change?
Thanks in advance for any guidance!
Hi, @Brian Bailey
Welcome to Atlassian Community!
Such behavior is possible if the project has a Priority Scheme assigned that includes only one priority option.
Check project settings, Priority Scheme. If it's the reason - just modify this scheme, add required Priorities.
Checking of project settings requires Project Administrator permissions.
Changing of Priority Scheme requires Jira Administrator permissions.