how to view all the completed sprints in burndown chart? Currently able to view only one out of two sprints. Kindly help.
Hi @Shanmuga Priya ,
Burdown chart is a sprint specific report and you can't have a view for all sprints. You need to select one of your sprint and take a look to the related chart associated. (https://www.atlassian.com/agile/tutorials/burndown-charts#:~:text=What%20is%20a%20burndown%20chart,work%20in%20the%20time%20available.)
Hope this clarifies,
Fabio