how can I assign sprints to a fix version?

hdlk forex
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 18, 2022

hi guys

how can I assign sprints to a fix version?

I don't want assign issues to release directly . in fact I wanna assign issues to sprints then assign sprints to a fix version.

2 answers

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 18, 2022

Welcome to the Atlassian Community!

That's not what versions or sprints are for.  There's no way to associate a sprint with a version directly, versions are markers for issues.

If you want to equate them directly (give a sprint a version), then there's a really simple option - stop using versions, you don't need them because the sprint is the version.

bart May 21, 2023

I'm trying to resolve this now where I'm not sure how to name fix versions as we move to mutliple releases in a sprint - your comment makes sense. However I need to solve stakeholder management about what version/release/when a feature (epic) will be done. The current dashboard shows planned targets per monthly releases (fix versions)

Any suggestions on what to use in the case of multiple releases in a sprint which may not equate to a feature/epic being complete in the sprint ?

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 23, 2023

I think the best option is to automate something - two things I'd do:

  • when a sprint is created, create a version with the same name (in all projects that the board includes)
  • when an issue is moved to "done" during a sprint, select the version for the current sprint on it

I don't think you can do either of those with automation unfortunately, I think you'll need a scripting app for it (I'm obliged to yell "Scriptrunner" at this point because I work for Adaptavist)

0 votes
Tom Lister
Community Champion
December 18, 2022

Hi @hdlk forex 

I see this would make sense to do in some setups. But sprint and version are usually different ideas. A sprint is an iteration of work. A version/release usually has some external meaning.

Unfortunately Fix Version is an issue field so has to be applied to each issue individually.

You could however try bulk applying the fix version once you have added all planned issues to a sprint.

You can use JQL to get a list of all issues in a sprint

project = BLAH AND sprint = "Sprint V1"

Sprint

You can then use the bulk change option to add a fix version to all issues.

You may need to specify the project as Fix version has project scope and all selected issues must belong to the same project to be able to bulk update it.