I work on a next gen project and i dont have the field "orginal estimate", how can i get this field? i must it to my work as a project manager.
Thanks
Hi @Yael
Time Tracking (i.e time logged) is available in Next-Gen projects. You can visualise this field per issue type by going to Project Settings > Issue Type, selecting a Type and ensuring the "Time Tracking" field is visible in the Context Fields.
The Original Estimate field however is not available; the only estimate field in Next-Gen today is Story Points.
You can vote / watch the suggestion for this at JSWCLOUD-17248.
Ste
Hi Yael,
You Have to enable the "time tracking field" and add "time tracking" field in to the screen.
Then you will get the original estimation.
Thanks
Ramesh