can we view the burndown chart for the future sprints and backlog of a project?

tinku
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 21, 2017

By using the above question I want to predict the project's completion dates by teams velocity

1 answer

1 vote
Thomas Schlegel
Community Champion
March 21, 2017

It doesn't make any sense to view a burndown chart for a backlog. There is no burndown and there is no start and end date for the storypoints to be calculated, this doesn't work.

Same for future sprints, they have no start and end date, so a burndown can't be calculated.