Working with Sub-Tasks on Kanban Board?

Fabian Neve
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 5, 2019

Hi all,

we want to work with sub-task and kanban boards. The sub-tasks were displayed, but cannot be transitioned to another status via drag-and-drop.

As you can see in following screenshot, by holding the sub-task the columns will not be highlighted.

2019-02-06 08_36_34-Expendables - Agile Board - Swisscard JIRA.png

The statuses are mapped properly, there aren't any issues left in the Kanban Backlog. Sub-Tasks uses the statuses "OPEN" and "IN PROGRESS", so I thought this should work.

2019-02-06 08_41_27-Configure Board - Swisscard JIRA.png

How are you working with Sub-Tasks on a Kanban Board?

Thanks

Fabian

1 answer

1 vote
Warren
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 5, 2019

Hi @Fabian Neve

It sounds as though you have a different workflow for your sub-tasks and possibly there isn't a transition set up for just the sub-tasks.

Go to Project settings then Workflows and see if there is more than one workflow listed. Below you can see a screenshot of my project, which is showing that all issuetypes follow the same workflow

Screenshot_3.jpg

Fabian Neve
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 6, 2019

Hi @Warren

Thanks for your answer. We use different Workflows for Bugs, Epics, Stories and Sub-Tasks.

2019-02-06 10_43_49-Project Development Agile - Workflows - Swisscard JIRA.png

Bug, Epic, Story work fine, but not Sub-Tasks. 

Is that an Issue? The Sub-Task uses a standard workflow, the statuses are mapped in the kanban board.

2019-02-06 10_46_04-Project Project settings - Workflow for Sub-task - Swisscard JIRA.png

 

 

 

Thanks

Fabian

Suggest an answer