Vijay Nagarajan
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 7, 2022

I was using company managed workflow for all my projects. Was able to see the following workflow before (Open - Assigned - Resolved - INtest - Verified - Closed). But i only see the fllowing workflow now for all my new projects (Todo - Inprogress - Done). I cant find the old work flow any more.

1 answer

1 vote
John Funk
Community Champion
November 7, 2022

Hi Vijay,

When you create a new project, it will attach the default workflow to it, if you do not create the new project based on an existing project. 

However, you can still attach the new project to the old workflow by going to Project Settings > Summary then click on the name of the Workflow Scheme.

Then click on the button to Switch Scheme and select the old scheme. 