Why remaining time of a closed subtask does not go to zero?

Sirin M February 23, 2017
Hi All,
I've got a question related to Jira.
Why remaining time of a closed subtask does not go to zero?
I have to manually set it to zero.
Could you advise me on this?
Thanks.

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 23, 2017

Duplicate of https://answers.atlassian.com/questions/56991186 which has an answer.  (Answers is creating a lot of duplicate questions at the moment, suspect it's related to the spam-bot attack in progress)