I have estimates in the subtasks but somehow they don't show up.
Hi @ana and welcome to the Community!
This is a common pitfall indeed in the way how Jira works. Your estimates should always be at the parent level (so on your stories or tasks) and not on your sub-tasks. Jira does not take those into account.
The checkbox that says include sub-tasks will consider the time spent from your sub-tasks, but not the estimates.
Hope this helps!
Welcome to the Atlassian Community!
Scrum does not say anything about sub-tasks, it only looks at sprint items. In Jira, sub-tasks are a fragment of a larger piece (the story), so putting estimates on them makes little sense. Jira only looks at the sprint items.
Kanban is similar - it doesn't do sub-tasks at all, so if you create them, they look like individual items. And, the estimate is by card count, not time or points.