The Jira Cloud documentation (at that link and in several other places) describes the Kanban backlog as being tied to issue status:

* In the "Columns and statuses" page for your board, there is a Backlog column.

* If you move statuses to the Backlog column, issues with those statuses will not appear on the board; instead, they will appear on the Backlog page.

After enabling the Kanban backlog for my project today, it doesn't seem to behave this way at all. Instead:

* There is no Backlog column on the "Columns and statuses" page.

* I have a separate Backlog page as shown in the docs, but it works differently. I have "Backlog" and "Board" sections instead of "Backlog" and "Ready for Development". Moving issues in and out of the backlog does not affect their status. Instead, it seems to just toggle whether they're visible on the Board or not.

* Moving issues in and out of the backlog doesn't even show up on the Activity for the issue - it just says I ranked it lower or higher, which seems to be talking about the position in the list in either "Backlog" or "Board".

I can't find any documentation that describes it working this way.

I also have no idea how to automate management of my backlog based on this - for example I'd love to automatically move tasks out of backlog and onto the board based on their due dates, but I don't see a property to modify on the issue to actually achieve that.

Can anyone help me figure this out?

 

EDIT: I played around with this a little more, and from what I can tell the difference appears to be in "Team-managed" versus "Company-managed" projects. My company-managed project behaves as described in the documentation. However, I still can't find any docs that describe how it's "supposed" to act as a team-managed project, or how to automate moving tasks out of the backlog. Do I just have to create a whole new project for that feature?

1 answer

1 accepted

1 vote
Answer accepted
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 3, 2024

Hi @Geoffrey Hicks -- Welcome to the Atlassian Community!

You are correct: configuration of the backlog differs for company-managed and team-managed projects.

For team-managed, the backlog is enabled as a "feature", and whether or not an issue appears on the board is managed from the backlog view.

Please look here to learn more: https://support.atlassian.com/jira-software-cloud/docs/enable-agile-features-in-team-managed-projects/

Kind regards,
Bill

Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 3, 2024

And also...

I just noticed your other question about automating the move of issues from the backlog to the board.  That is possible using a Jira Automation rule with the rule action "Move Issue to Board".

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
TAGS
AUG Leaders

Atlassian Community Events