I'm testing a jira automation that needs to do something on 'complete sprint'. I created a bunch of issues on this test sprint that I need for the testing. However when I reopen the sprint, I can't see my issues on the board or in my backlog under the sprint that is just reopened. The weird thing is that after refreshing 20+ times or waiting. Sometimes they suddenly reappear. But it's very frustrating to have to wait an unknown time. A couple times they didn't reappear for more than an hour.
Anybody knows why this happens and how to work around it?
Would also appreciate better methods on how to test this kind of stuff!
Thanks in advance.
Hello @Tiemen Blankert
When you close the sprint you must choose what to do with the incomplete issues - move them into the Backlog or move them into another not-started sprint. Which are you choosing to do?
Issues will keep track in the Sprint field of all the Sprints to which they were added and remained in when the sprint was Completed. The field retains multiple Sprints, not just the current sprint.
So, when you reopen a completed sprint, the issues that were completed within that sprint will display again on the board and in the Backlog view because they remember they were in that sprint, and it is now active again.
The message about issues being moved back into the sprint regards the items that were incomplete when you completed the sprint. If they are currently in the Backlog or in another sprint that has not been started, then they will be included in the reopened sprint again. If, after the sprint was closed and before it was reopened, you moved those issues into another sprint that was active or that you started, then you would see a message about issues not being able to be moved back into the sprint you are reopening.
In my own testing of this I saw discrepancies in the display of the reopened sprint contents between the Backlog view and the Board view. The Backlog view showed the correct contents but the Board view did not. I did not wait very long to check this. It may have been a browser caching issues. I did not try to debug that specific discrepancy.
thanks for this answer and i definitely learned something from it but it is not what i mean. I choose for the incomplete issues to be moved to another sprint but thats not my problem. The problem is that the completed/resolved issues are supposed to move show on the reopened sprint. They eventually do, but it takes a variable time for them to show up. Refreshing the page or opening it in another window or logging in and out doesn't work. It somehow just takes a while and I wanted to know if there was a way to make them show up quicker again.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you for the clarification. As I mentioned I saw discrepancies in my own testing when reopened sprint contents displayed correctly immediately in the Backlog view showing both closed items in the sprint and any that were moved back into the sprint, but the sprint content did not display immediately in the Board view.
I had the same sort of experience as you.
I did not try to debug the reason for the delay in getting the correct issue display in the Board view.
I recommend that you report the issue to your Jira admins and ask them to escalate it to Atlassian Technical Support.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
From what you describe, the work items may be marked as resolved and so missing on future tests with the sprint and board. You do not describe specifics of the process, rule, how you "reset" tests, etc., so I am guessing a bit here.
When testing automation rules, particularly more complicated ones which do things to work items on Sprint started, completed, etc. events, I may use these practices:
Kind regards,
Bill
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for the practices/tips!
What I meant originally is that when you have resolved issues in a completed sprint, then reopen that sprint, the resolved issues should return back to the board. And they do, but it takes a random amount of time for them to show up and I was wondering why that happened and how to speed it up/force if possible. Sometimes I had to wait more than an hour.
To reproduce:
make a test sprint-> put a bunch of issues in the done/resolved category-> complete the sprint -> reopen that sprint -> check back on the backlog and observe that those issues are missing.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I am uncertain what could cause that symptom...other than it is cloud storage and updates may need to propagate through the work items.
Have you checked if other automation rules or marketplace apps are making changes to the work items? You can do that by find some example work items with the symptoms and then reviewing their change history.
Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
To have the work items burned and mark as completed in a sprint.
The final workflow status has to be in the last column of the sprint board, otherwise if this is not the case, the work items are bot considered done in the sprint.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello @Tiemen Blankert
Completing and reopening isn't the same. Once the sprint gets completed, that's it. Those issues from the active sprint disappear, unless you've closed the sprint with some of the uncompleted work. In that case, all uncompleted work is moved back to the backlog to be added to the upcoming sprint.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for the reply! I'm very new to Jira so I know im probably misunderstanding a lot.
But I wonder then why if i wait a while, the issues in 'done' dó return to the sprint? Also why do I then see this text when reopening a sprint:
"12 issues will be moved back to the sprint you're reopening.
Sub-tasks are not included in the total(s) above, and are always included in the same sprint as their parent issue."
note that those 12 issues are all in the 'done' category
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It makes sense for the issues to get back to Backlog when you are reopening a sprint. This is something that shouldn't really happen in Scrum. But still, you are reopening the sprint and @Trudy Claspill is correct with everything that she mentioned.
As for the time taking of the issues to return it's more on the backend response of the server.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It's happening for everybody in my jira environment. It sometimes takes 15 minutes and sometimes more than 2 hours.
What do you mean with "Network part of your development console"
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
When you go to Settings of your browser you have the option Development console. In there you have the Network tab that you can use to see how frequent these issues arise.
Is your department using a VPN?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.