Hello,
I want a create a linked tasks.When ı create the tasks otomatically two new tasks must be created and otomatically assigned to the related person with task.
How can ı do this?Can you help me please?
Hi Enis,
Yes, you can do that with an Automation rule. Here is some more information to help get you started:
There are two types of automation:
Automation Basics: https://www.atlassian.com/software/jira/guides/expand-jira/automation
You can do this via global rules to apply to all projects also. You'll need to be a Jira Admin/Site Admin, go to Jira Settings > System > Automation Rules (left-hand menu).
For more on using Automation For Jira see these help pages.
Jira Automation Template Library to help get you started quickly:
https://www.atlassian.com/software/jira/automation-template-library#/labels/all/customLabelId/1453
You will want to create a rule with an Issue Created trigger.
Then you can create the new tasks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.