Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Whats the best way to handle many small requests during a one week sprint period?

Roni Hoffman June 14, 2020

We have a small number of developers in our team.  And we are getting many smaller requests/tasks that come up during the week.  I want to have a weekly sprint with items to be worked on but we can't ignore the requests that come up during the day/week.  Generally the smaller requests should take priority.

 

Is there a proper way to handle this?  Should I be adding each request as a ticket and then moving them into the sprint board?

 

Thanks!

1 answer

1 accepted

0 votes
Answer accepted
Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
June 15, 2020

Hello @Roni Hoffman

Thank you for reaching out.

If the small requests worked through the week will impact the Sprint estimation and should be considered there, the best approach would be to create a new issue and add it to the Sprint with the amount of time estimated.

Issues added after the Sprint start will be displayed with an * in the reports and will be considered scope change, but will properly count to the Sprint estimation.

If the amount of time spent on each request are not relevant individually, you can also create a single request with the total amount of time spent on all the small requests, optionally creating sub-tasks under that parent issue to properly register the work done.

Let us know if you have any questions.

Roni Hoffman June 15, 2020

Thank for this

Roni Hoffman June 19, 2020

Hi @Petter Gonçalves 

If I add say 10 unplanned items during a week long sprint, is there a way for Epics and/or other tasks to auto adjust their time estimation or expected due dates?

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events