What triggers time to first response measurement?

Drew Rice
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 20, 2018

I am using the Time to First Response gadget in JIRA to track my team's SLA. When tickets are created my team typically will update the status of a ticket before commenting on it so I was wondering - is the response measured by the first time a comment is placed on the ticket or is it the first time the ticket is moved to a different status? My assumption is the former.

 

Thank you.

1 answer

1 vote
Thomas Deiler
Community Champion
February 20, 2018

Dear @Drew Rice,

any change to the issue after an issue was created will trigger.

So long

Thomas

Drew Rice
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 20, 2018

Awesome thank you! I'll let my team know that they can maintain status quo and just move tickets into a new status when they're being worked as opposed to commenting on a ticket saying it's about to be worked. I appreciate it.

Sam Ferguson July 3, 2019

@Thomas Deiler Is this still the case? Based on my use of the gadget it appears that Time to First Response is measured by the first comment.

For example, it appears that adding an attachment does not count as a first response.

Is there any documentation you can point me towards for this? Thank you.

Like J_ Sakurai likes this
Thomas Deiler
Community Champion
July 13, 2019

Dear @Sam Ferguson ,

you are right. It is written here. Just the comment.

So long

Thomas

Like K_ Yamamoto likes this