Hello community,
I have a question regarding the WBS Gantt Chart Plugin (version 9.14.4.1):
I have activated the auto-correct schedule function and now the start and end dates of some issues have changed, although I have only changed the start and end date of one issue. Is there a way to undo this?
I only wanted to change the start and end date of one issue.
Is it possible to restore the original dates by resetting the GANTT to yesterday's date?
Personally I am unable to provide a direct answer however this is a third party app
while you may get lucky in regards of third party apps and responses (sometimes there are either users of the app or the vendor themself on community) more often than not it’s best to open a ticket with the vendor directly. This is because the marketplace has 1000s of apps so not all of them have users accounted for on the community as atlassian doesn’t make them.
if you haven’t already I’d recommend opening a ticket here: https://www.ricksoft-inc.com/contact/
best,
Clark
Hello @Dominik Hermann ,
I'm afraid it is not possible to restore the original dates because these dates are stored in Jira custom fields.
When you turn on the auto-correct schedule function, then it works for all issues on the Gantt Chart, meaning all issues that had inconsistent start/end dates were corrected.
The only way to restore the value is to check the issue history one by one and change the value manually.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.