Velocity Chart - Commitment not showing on my first sprint

Harpreet Singh
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 1, 2021

Hello,

 

Velocity Chart - Commitment not showing on my first sprint. Please suggest

We did change the estimates on the first sprint - I believe that could be the reason.

 

any other information will be helpful.

Harpreet 

1 answer

1 vote
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 1, 2021

Hi @Harpreet Singh -- Welcome to the Atlassian Community!

When you started the sprint (date/time) were the stories sized with story points?  If not, the total was zero (0) at the time the sprint started, and so was the "commitment" for the report.

In that case, a tip is to complete your sprint planning/sizing before starting the sprint in Jira.

Kind regards,