Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Understanding my sprint report

Jennifer Tucci
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 15, 2021

Forgive my "newbie" question, but I am having a tough time figuring out my sprint report. We use original time estimate as our statistic and track time spent (why the green line is there). 

Capture.PNG

 

Here is how I am reading this: At the beginning of the sprint, we estimated around 325 hours of work. We quickly added tasks to the sprint, taking us up to 600-ish hours. By around July 7, we hit those 600 hours and kept going! BUT, we ended up carrying over close to 400 hours of time in our remaining values?

 

This seems like we are super inefficient, which is not an accurate picture, so now my question is if we are utilizing our sprint ticket fields properly. We use original time estimate and then we track time to the tickets via third party plug in, and I do get a "time spent" and "remaining time" estimate in our tickets. Capture2.PNG

 

Can anyone help me with my above description (if I were explaining this chart to an executive) and if I am correct with all my fields? Many, many thanks!  

 

2 answers

1 vote
G subramanyam
Community Champion
July 15, 2021

Hi @Jennifer Tucci welcome to the Atlassian community.

Here's the more detailed explanation about the Jira reports and their explanations 

Stay safe and stay healthy.

0 votes
Jack Brickey
Community Champion
July 15, 2021

One thing to be sure to do is set the remaining time to 0 for all issues that are marked done. This includes if you have statuses like cancelled, etc. Moreover, ensure the remaining time is always as accurate as possible. Finally, as you pointed out try to address future instances of sprint churn. 😉 basically what I would take away at first glance is that you initially effectively estimated your teams velocity but then allowed for doubling of the capacity, I.e. your red line burned down to the original estimate.

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events