Unable to see closed stories on portfolio plan

Namrata
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 30, 2023

I wish to track epic progress. Actual progress is somewhere around 23% if i track on excel but on jira it is only 13% because it is not considering closed stories. How do I get exact percentage of completion if closed stories are not visible even though i have selected status as closed, to-do and in progress. 

 

Help me, it's urgent

2 answers

0 votes
Namrata
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 1, 2023

Resolved after including Resolution field. Thank you.

0 votes
Florian Bonniec
Community Champion
May 30, 2023

Hi @Namrata 

 

Are the closed story using a status that have Done status category ? Also have you set a resolution when a story is closed ?

 

Regards

Wesley Payne May 30, 2023

Hi Florian, 

 

I hope you are doing well.

I work with Namrata, so the workflow ends with a closed column and closed "status". i just noticed that their is no resolution field on the screen scheme.

 

If i add that field to the screen scheme and it is captured would that assist with the above? 

Suggest an answer

Log in or Sign up to answer