US in Scrum and Kanban Board in one Project - what happens to US in Kanban Board if Sprint is closed

ernst_herrmann
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 23, 2024

Kanban Board and Scrum Board in my Project.

A US is displayed in both boards.

Now I close the sprint in Scrum and send the undone US back to backlog - what happens to the US which is in "to do" in the Kanban Board?

1 answer

0 votes
Walter Buggenhout
Community Champion
May 23, 2024

Hi @ernst_herrmann and welcome to the Community!

That depends on the board filter behind your kanban board, but - unless your filter includes a reference to the active sprint in your scrum board - most likely nothing.

Boards are just views on issues and a user interface that adds some functional capabilities to manipulate the issues. As removing an issue from a sprint just updates that issue's sprint field, nothing happens to how the issue is displayed on your kanban board until it no longer matches that board's filter.

Hope this helps!

ernst_herrmann
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 23, 2024

Thanks, it helps indeed.