Hi, I have a problem with one task issue that is not calculating the remaining time correctly.
The original estimate is 3d, time logged is 7h, and the remaining time appears to be 0.
Does anybody know why is this happening? It only happens with this issue.
Thanks!
From the image it shows >2w of logged time. Can you check the worklog tab on the issue?
Hi Jack,
The time logged is 7 hours. The 2w you see it´s just what it comes as deffect when you open the time tracking, is not real, just an indication and example of the time format you have to use when logging your time. See screeshot below:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I suspect that the individual that logged time entered 0 in the remaining time. That is in a scenario where I've seen this occur. Unfortunately the history of the worklog does not illustrate this.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Apparently he didn´t entered 0 in the remaining time. This continue to be a mystery for us.
I appreciate your help, thanks a lot! :)