Hi @[deleted]

There isn't a roll-up by default - time estimates on sub-tasks can be rolled up to story-level, but you'd need an app to roll estimates up from stories to an Epic (unless you have Jira Portfolio, where you can view it on the plan/scope view)

You could try:

  • An app which directly address the issue, such as Epic Sum Up
  • Scripting a field to provide this information using an app such as ScriptRunner - questions and answers like this one can help you create this

What is possible on each app does depending on your host type (i.e Cloud, Server, Data Center) - check out each app's documentation to see the differences!

Ste

Deleted user April 21, 2020

Hey Tahnks for the response!!!

Like Ste Wright likes this
Ste Wright
Community Champion
April 26, 2020

No worries :) - if this answer was helpful, could you press "Accept Answer" so other users know when searching for a similar answer?