We recently migrated from Jira Data Center (DC) to Jira Cloud.

After the migration, some teams were unable to start their sprints that were scheduled to begin on July 6. When users attempted to start the sprints manually, they found that the "Start Sprint" option was not available in Jira Cloud.

Additionally, we observed that the sprint start date had automatically changed from July 6 to July 5, which is one day earlier than expected.

As part of our investigation, we verified the time zone settings in both Jira Data Center and Jira Cloud under the System settings. In both environments, the Default User Time Zone is configured as (GMT-08:00) Los Angeles, so there does not appear to be any time zone mismatch at the system level.

 

The sprints are 

  • Fw2_FY26_Jul_1_Lanterns
  • Fw2_FY26_Jul_1_Sunstars

 

2 answers

2 accepted

2 votes
Answer accepted
Marc -Devoteam-
Community Champion
July 6, 2026

Hi @QueenMary Bastin 

There are issue in relation to automation and other topics in the Atlassian Cloud, see Atlassian Status

0 votes
Answer accepted
Gor Greyan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
July 6, 2026

Dear @QueenMary Bastin

The issue is fixed; all services are marked as operational on the status page.
Check again if the issue is still actual or not.
https://jira-software.status.atlassian.com/

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
PERMISSIONS LEVEL
Product Admin Site Admin
TAGS
AUG Leaders

Atlassian Community Events