Summary visualization - only for 7 days?

Lucia
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 19, 2023

Hi! I would ask how I can configure the summary visualization to show me the full status project, not only the last 7 days, it´s possible? Thanks!

1 answer

0 votes
Trudy Claspill
Community Champion
April 19, 2023

Hello @Lucia 

Welcome to the Atlassian community!

It is not currently possible to configure the time period for the Overview tiles. Per this article...

  • Overview cards - these cards provide an overview of recent activity within the project by displaying the number of issues that have been completed, updated and created in the last 7 days as well as the number of issues due in the next 7 days.

I have not found a change request asking for that specific configuration option yet. If you are working with a paid Jira subscription your Jira Administrator could open a support case to ask Atlassian Support if they know of a change request for that functionality. Or you can search for yourself here and open one if you can't find one.

https://jira.atlassian.com/secure/Dashboard.jspa

You can also construct a separate Jira Dashboard independently to present the information for the lifetime of the project.