Successors / Predecessors in Advanced Roadmap

Alex Shirokov
Contributor
February 10, 2022

Hello, 

I have a task "A" that starts on March 1, 2022, and ends on March 5th, 2022. This task is a predecessor of task "B" which starts on March 10, 2022. The lag time is 5 days between the tasks. 

Now the puzzle starts... When I change the start date of Task "A" from March 1 to March 8th the start date for task "B" remains the same BUT it should be automatically be updated to March 13th. 

Please, explain to me what I am doing wrong

Thank you in advance

 

2 answers

0 votes
Muhammad Moazzam Hassan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 25, 2023

It can be achieve via automation.

Step 1: Create Custom Field (Label Type) name as predecessor and add the issue key of predecessor issue.

Step 2: Create automation rule when Predecessor field edit and is not empty then Lookup issue for and use the smart value of Predecessor field.

Step 3. If lookupissue size equals 1 then edit the current issue Actual start date with a smart value "{{lookupIssues.Actual End Date.plusBusinessDays(1)}}" and set the end date as {{lookupIssues.Actual End Date.plusBusinessDays(issue.customfield_10212)}}.

25-September-2023 (157).png25-September-2023 (159).png

0 votes
hung.nguyen
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 26, 2022

Am I considering that the connection between Task A and Task B is block by/ is blocked by?

If yes, i think there's no way for the automation.

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events