SubTask register worklog / Registros de subtasks en worklog

Eduard Diez
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 17, 2018

How do people estimate the SubTasks? and how do you do the Stories also in sprints? We are starting in JIRA and I would like to know the usual and correct way of working in the ATLASSIAN world.

Thank you

 

Como hace la estimación de las SubTasks la gente? y cómo lo hacen de las Stories tambien en sprints? Estamos empezando y me gustaria saber la forma habitual de trabajar del mundo ATLASSIAN.

 

Gracias

3 answers

3 accepted

1 vote
Answer accepted
Eduard Diez
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 18, 2018

Por lo que he leído la SAFe aconseja que una Story point sea de 1 dia = 8 horas de trabajo por persona.

Aunque realmente es la relación entre cantidad de tiempo que se requiere en función al número de personas que trabajan (Personas/hora, hora/Persona , Personas/mes), usa tres variables fijas, que serían el tiempo, número de personas y disponibilidad de las mismas.

Es mucho más complejo de lo que pensaba, pero supongo que al final se acaban ajustando los Story points y que cada equipo acabe dando los tiempos estimados.

 

  -----------------------------------------------------------------------------------------------------

SAFe said and advise that a story point was ​​1 day = 8 hours of work by person.

Although it really is the relationship between the amount of time that is required depending on the number of people who work (People / hour, hour / person, people / month), use three fixed variables, which time, number of people and availability of this people.

It is much more complex than I thought, but I suppose that in the end the points of the story are adjusted and that each team ends up giving the estimated times.

1 vote
Answer accepted
Tarun Sapra
Community Champion
July 17, 2018

Hello @Eduard Diez

You have asked a pretty broad question and honestly you should have an Agile coach on board for first few months of your Agile journey. Atlassian tools support Agile processes but you should first see what will works best for your team based on the maturity of the team and then configure the tools to support your process instead of tools dictating the process it's best for tools to support the right process.

1 vote
Answer accepted
Mirek
Community Champion
July 17, 2018

A lot to say here and I think the best way would be to read Agile Tutorials that include all the basic information how it is done in JIRA - https://www.atlassian.com/agile/tutorials