Structure Agile Gantt Chart plugin question

Tina Park
Contributor
January 20, 2023

I know this is an external plug-in but thought I'd give it a shot asking this community. 

 

Is it possible to set up an Agile Gantt Chart for multiple Jira projects that do not share a board, therefore do not share sprints. 

 

For example, I've set up Advanced Roadmapping in Jira this way, I can set it up via a custom JQL for issue source with some loss of functionality, ie. I can't assign sprints directly from Roadmap. I can view the sprints however on the Roadmap. Would Structure Agile Gantt be able to do this if not the ideal scenario above?

1 answer

1 vote
David Niro
Atlassian Partner
January 25, 2023

Hello @Tina Park ,

If I understand your use case correctly, yes, this is possible using Structure and Structure.Gantt.

You can visualize issues from multiple projects and also assign them to the Sprints from their respective boards.

Please feel free to reach out to us directly if you would like a demo or have any questions about starting a free trial! We are available via support@almworks.com or through our customer portal support.almworks.com

Best,
David