Giselle Rebeca Thomé Gataz May 26, 2025
I created an automation to create tasks that repeat in an epic. Is it possible to automatically insert the "start date" from the completion data of the previous task that is a predecessor for calculating the end of the epic? The intention is to have visibility of the start and end of all tasks as we have in "MS Project" the overview of the end of the project.

1 answer

1 vote
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 26, 2025

Hi @Giselle Rebeca Thomé Gataz 

The answer depends upon how you are creating the Tasks in the rule:

  • when creating them one-by-one by precedence, with no branching in the rule, the answer is "yes": the rule may refer to the most recently created one to set the date value
  • however if the rule uses branching, the answer is "no": such branches process in parallel and they is rarely a way to create / update them in a defined order

 

Kind regards,
Bill