Sprint title transferring across boards/project

Natalie_Mihigo1
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 11, 2023

I'm a part of two boards and noticed when the  sprint names are changed on one board they get reflected on the alternate board.  Not sure if this is a bug. 

 

1 answer

2 votes
Mark Segall
Community Champion
September 11, 2023

Hi @Natalie_Mihigo1 and welcome to the community!  This is by design as sprints are not tied to projects or project boards. 

An example use case of where this is a desirable feature is a situation where you have a complex application made up of multiple micro services.  Each micro service is managed on a specific project to enable uniquely linked code repos.  However, only one or two teams actually manage the overall application.  In this use case, it would be desirable for the sprint to span multiple projects so that the team can track the work across the application in a single sprint rather than trying to navigate one sprint for every micro service.