Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Sprint raport status of tasks

bartlomiej.jochym
Contributor
February 28, 2024

Hi,

Is it possible to separate completed subtasks from others?

When I want to create a sprint report of 1 story with 3 subtasks (2 completed and 1 to  do), the report treats our story as "Issue Incomplete" even though two subtasks have been completed.

 

Story

Screenshot 2024-02-28 at 23.20.05.png

Report

 

Screenshot 2024-02-28 at 23.18.23.png

 

1 answer

0 votes
Danut M _StonikByte_
Atlassian Partner
February 28, 2024

Hi @bartlomiej.jochym

The report is correct, because the story is incomplete, due to the fact that not all the sub-tasks were completed. If you want the issue to appear as completed, try to manually change its status to Done. 

Danut.  

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events