As per screenshot.
I have child items allocated to future sprints. I expect the epic to reflect that in its rolled up date, but it doesn't:
It appears to work as expected when looking at the timeline on the board itself.
Also, any idea why I can't select and change sprints in the timeline view (drag and drop) from Plans, like I can from the board timeline? This feels like a backward step to me.
You are correct, this is also visible in the plan, as the dates in the Epic are set and not based on roll-up.
Epic should never be added to a sprint.
Here is a kb with options to remove historical sprint values from a work item; how-to-remove-previously-closed-sprints-from-an-issue
This is expected in Jira Plans. Epic roll-up dates don’t always extend based on future sprints, even if child issues are assigned there—those dates show more reliably on the board timeline.
Drag-and-drop sprint changes aren’t supported in Plans by design; sprint assignment is meant to be done from the backlog or board, not the Plans timeline.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
So i think I worked it out. Looks like the epic was assigned to a sprint, that is now completed.
I can't figure out how to remove the historical (closed) sprint that it was assigned to in the past. I think that might be preventing the roll up of the child items sprint dates.