I have an epic from which several tasks are attached (epic link), in roadmad it allows me to adjust the schedule of the epic, however it does not allow me to adjust the schedules of the tasks that are attached to this epic.
There is some configuration to be able to do this.
Thank you very much
If you are using a Standard Jira Cloud subscription, Basic Roadmaps supports showing the timeline for only Epics. Showing the timeline for child issues is not available.
You would need to upgrade to the Premium Jira Cloud subscription to get Advanced Roadmaps to see the timeline for child stories on the roadmap.