we are manually generating these reports by pulling data (either by export or manually) in JIRA to create these Excel charts:
Production support spent vs estimated (HOURS spent vs. HOURS estimated
This is the aggregated view of the hours logged against tasks with the PRDSupport component against the hours extrapolited from points.
> Projects in Sales Engineering
> Hours logged for stories with the PRDSupport Component
>> By Project and aggregate
> Points of stories with PRDSupport Component * 8 to get hours budgeted.
Note: for us, 1 point= 1day
Business Point Spent vs Estimated
I would like to see the completed stories grouped by business area, per project and across Sales Engineering projects.
> Projects In Sales Engineering
> Points completed per project
> by Business (component in (FinPrd, ES, Tradebook)
Stories Completed vs Committed
> Per Project
> Aggregate for Sales Engineering