Remaining Estimate and Time Spent not available in board Estimation

Sarah Gearinger
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 12, 2025

Hi, I'm looking to set up a Jira board that uses "Remaining Estimate and Time Spent" as the estimation metric for planning. I'm following this article: https://support.atlassian.com/jira/kb/how-to-view-remaining-time-estimate-on-issues-from-backlog/

However, I don't see the "Remaining Estimate and Time Spent" radio button as described in this article and other support questions. Screenshot of my settings options below.

I've already confirmed the following:

  1. This is a company managed Space
  2. This is a scrum board
  3. Global time tracking is enabled
  4. Time Tracking field is available on all screens

So, what I need help with, why isn't "Remaining Estimate and Time Spent" available in my board settings under Estimation?Screenshot 2025-11-12 150447.png

3 answers

0 votes
Andrea Santi November 28, 2025

I have the exact same issue.

estimate.jpg

 

And this is causing a super-weird behaviour. In existing spaces the burdown charts works

old_project.jpg

 

In newly created one the time spent shown is always zero!

time_spent.jpg

 

Something changed? Can someone help here please?

0 votes
Sarah Gearinger
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 13, 2025

Any chance this was removed recently? I've seen screenshots and articles where this setting should be available. It's just not available in our Jira Cloud instance.

0 votes
Sherwin Soriano
Contributor
November 12, 2025

 I don't think "Remaining Estimate" and "Time Spent" can be seen in that setting. You will only see those fields in the right panel of each ticket you are viewing.

Suggest an answer