Releases show Issues Done, In Progress, and To Do. None are correct according to our issue status.

russell fleming October 26, 2018

In all my releases the issues counts for done, in progress, and to do are not usable as they are not correct. I need to know how to configure what status are counted in these fields so that they are usable.

For example, in my workflow we start with Open, and then Approved, and then In Progress. Approved issues show in the Done category. I want then counted in the to do category as that is more appropriate.

1 answer

0 votes
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 26, 2018

Hello,

Go to Issues -> Statuses. Find the Approved status, click edit and change the Category field to To Do:

Screenshot 2018-10-27 at 07.20.57.png

russell fleming October 29, 2018

I don't have those menu items. Seeking administrative help for if this is a privilege issue.