Hi there,
I'm a little unhappy with the report Release Burndown. After realizing this bug is effective https://jira.atlassian.com/browse/JSWCLOUD-16224 I noticed another issue:
We started a new version some time ago but the original estimate at start of version is shown with 0 although all issues in it have story points. But after having started the first sprint (although the incorrect sprint as mentioned in the bug) the chart at least showed the correct sum.
Today we added an issue with 8 story points. This sum was just added to the remaining work and is not marked as 'added'.
But of course it would be a very helpful information to see what actually was added to the release.
Do you have an idea what I did wrong?
Thanks so much in advance.
Best