Release Burndown neither shows original estimate at start of version nor marks work added

Yvonne May 14, 2020

Hi there,

I'm a little unhappy with the report Release Burndown. After realizing this bug is effective https://jira.atlassian.com/browse/JSWCLOUD-16224 I noticed another issue: 

We started a new version some time ago but the original estimate at start of version is shown with 0 although all issues in it have story points. But after having started the first sprint (although the incorrect sprint as mentioned in the bug) the chart at least showed the correct sum.

Today we added an issue with 8 story points. This sum was just added to the remaining work and is not marked as 'added'.

But of course it would be a very helpful information to see what actually was added to the release.

Do you have an idea what I did wrong?

Thanks so much in advance.

Best 

0 answers

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
atlassian, team '25, conference, certifications, bootcamps, training experience, anaheim ca,

Want to make the most of Team ‘25?

Spend the day sharpening your skills in Atlassian Cloud Organization Admin or Jira Administration, then take the exam onsite. Already ready? Take one - or more - of 12 different certification exams while you’re in Anaheim at Team' 25.

Learn more
AUG Leaders

Upcoming Jira Events