Project Configuration: Workflow gets added to wrong issuetype in workflow scheme

Chris K
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 13, 2023

Dear Community,

We have created a uniform workflow for the issue type "Project", which we now want to roll out to the Jira projects that contain this issue type. The workflow should be added to the respective workflow scheme of the project. When testing in my test project, however, I already encounter a strange system behavior: As soon as I add the workflow to the "Project" issue type by clicking on "Finish", it is assigned (without an error message) to the "Subtask" (German: "Unteraufgabe") issue type (see screenshot below):

2023-06-12 09_55_40-Project Application Management Collaboration Tools - Workflows - Jira.png

I can't explain the system behavior at this point...

Am I missing something here?

2 answers

1 accepted

2 votes
Answer accepted
Radek Dostál
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 13, 2023

If you're editing this from the project - try doing it from Workflow Schemes administration page instead. The project side scheme editor can sometimes be a little funky, I think I came across this at some point and going through workflow schemes helped, but it was.. maybe a few cases, not sure if it will work for you too but worth a shot.

Chris K
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 18, 2023

Hello @Radek Dostál,

This helped! Thank you for the hint :)

Just sent some kudos to you. Congrats for reaching the golden Seed Level! ;)

Greetings Chris 

Like John Funk likes this
0 votes
John Funk
Community Champion
June 13, 2023

Hi Christian,

That's very strange. Are you able to click the Assign link and assign it to the Project issue type? And then remove the Sub-task? 

Chris K
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 18, 2023

Hello @John Funk

By clicking the assign link for the Project issuetype, the Story Issuetype gets assigned instead. So it gets even weirder...

Nevertheless, the hint from @Radek Dostál provided the solution in this case :)

Thanks for your help :)

Greetings

Chris