Hello,
I have a story with the story points estimated. Now, I want to set the Estimate hours inside the sub-tasks but I can't add the Estimate field.
Because of this, my Burndown Chart doesn't reflect the reality.
Anybody can help me with this?
Thanks,
Lucas.
What do you mean "can't add the estimate field"? Has an admin placed "time tracking" on the screens for the sub-tasks?
Yeah. Have a "time tracking" field but just allow a modal to edit "time spent" and "time remaining". How can I estimate the sub-task like a put hours and after log the work time to generate the burndown chart?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sorry, there was a problem with Community email and I missed your earlier response.
That is the "log work" screen, it is not the issue screen. Your admin needs to add time-tracking to your create and edit screen.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.