Only close the main ticket once the subtasks have been completed.

Antonia
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 26, 2025

Is it possible that the main ticket can only be closed when all subtasks are closed? Because currently, for example, we can create a change/task with subtasks, but then we can close the main ticket even though the subtasks are still open. To me, that doesn't make much sense.

1 answer

1 accepted

2 votes
Answer accepted
Shalini Pradhan
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 26, 2025

Hello @Antonia ,

Good day! Welcome to Atlassian Community :)

Yes, its possible via Workflow conditions. More details here: How to prevent Closing Issues with Open Sub-Tasks in Jira 

You can also use automation, more details here: Automation For Jira - How to write a rule to close a parent issue after all sub-tasks have been closed 

Thank you!

 

Antonia
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 26, 2025

Hi @Shalini Pradhan

thank you for your answer. So this site How to prevent Closing Issues with Open Sub-Tasks in Jira is not available (404 error),  but I will look at the other page, thanks!