On the Gantt chart, on the Roadmap I create the tasks but if a task starts at 9AM friday and ends at 6pm monday, it has a duration of 4 days and it should be 2 days.
Hi There,
Currently, next-gen project does not have a "Board settings" option, so it's not possible to configure the settings such as Working days.
We have the following feature request tracking interest in this:
Please make sure to adda vote to help us track interest per the Implementation of New Features Policy and you can watch the request to receive updates about the feature.