NextGen Issue Status not aligned with report

Yasmeen Abubakr
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 24, 2020

Hi, 

I am using Next Gen, and have customized the statuses on my board. I'm realizing that statuses which are not in the final column (Which we'd called 'closed') are popping up in the report as 'Complete' issues. When they aren't completed.

What could be causing this?

Thanks

1 answer

0 votes
Angélica Luz
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
July 28, 2020

Hello Yasmeen,

Thank you for reaching out to Atlassian Community!

When working on a next-gen project, tickets that have a resolution are the ones considered "Done".

With that said, if we move some tickets to the very last column, a resolution will be added, but if after that we add a new column as the last one, the resolution from the tickets won't be removed, it will still be considered as done. To fix that, it will be necessary to transition to another status and move back to the original column.

On the example below, Done was the last column and after that, I added another column called Resolved. It's possible to see that all the tickets on the Done column still have the resolution, even though it's not the last column anymore.

Screen Shot 2020-07-28 at 14.54.03.png

I'm not sure if that's what is happening in your case, so please, confirm if the tickets that are appearing in the report have a resolution or not. 

Regards,
Angélica

Suggest an answer